New Haven Harbor Navigation Improvement Study

                                 
 

The U.S. Army Corps of Engineers New England District is conducting a feasibility study and Environmental Impact Statement to examine navigation-improvements to the existing New Haven Harbor Federal Navigation project. 

The Corps participation in this study is authorized by a resolution of the Senate Committee on the Environment and Public Works dated July 31, 2007. This study was initiated at the request of the New Haven Port Authority and the Connecticut State Port Authority. The study is being cost-shared 50-percent Federal and 50-percent non-Federal with the New Haven Port Authority.  

The New Haven Harbor navigation project’s main ship channel, maneuvering area, and turning basin are authorized to a depth of -35 feet mean lower low water. The main ship channel is about 5 miles long extending from deep water in Long Island Sound to the terminals at the head of the harbor.  The channel varies in width from 500 feet (outer-harbor) to 400 feet (inner-harbor), and widens to 800 feet along the terminals. 

Deeper and wider channels, maneuvering area, and turning basin are needed to increase the navigation efficiency and safety of New Haven Harbor. To reach the terminals, larger ships must lighter outside the breakwaters and/or experience delays while waiting for favorable tide conditions, or both.

To view the Press Release please click here

To view the Draft EIS, please click here.


For more information, please contact the Project Manager, by e-mail or by calling (978) 318-8737

Updated: October 26, 2018



General Schedule

January 2017 - Scoping Meetings
January 10, 2018 Public Meeting

September  2018 Draft Feasibility Report and Environmental Impact Statement
October 2018 - Public Hearings
July 2019 - Final Feasibility Report and Environmental Impact Statement
November 2019 - Record of Decision