CONCORD, Mass. –
Vermont
Transco, LLC and New York Power Authority are seeking a permit from the U.S. Army Corps of Engineers, New
England District to conduct work in waters of the U.S. in conjunction with installation
of four transmission lines in Lake Champlain between Plattsburgh, New York, and
Grand Isle, Vermont. The purpose of this proposed project is to replace
deficient cables with new cables to maintain an electric transmission
interconnection between New York and Vermont.
The
proposed work will involve the replacement of seven existing cables on the
PV-20 electrical transmission line in Lake Champlain between Plattsburgh, N.Y.,
and Grand Isle, Vermont (a distance of 1.8 miles) with four
new subaqueous 115kV transmission cables. The cables will be installed in the
transition areas between aquatic and terrestrial portions of the project by using
horizontal directional drilling (HDD).
Temporary
11-foot by 25-foot gravity cells will be installed on the lake bottom at the
aquatic transitions to minimize turbidity and to confine drilling fluids or
cutting material that may escape from the drill holes. In depths less than 100
feet the cables will be installed in a trench about 4 feet below the lake using
a jet plow towed by a barge. In depths greater than 100 feet the cable will be
laid on the lake bottom without burial or protection. The work will temporarily
impact about 2.48 acres of lake bottom. The construction of a new Cumberland
Head Transition Station and new Grand Isle Terminal Station will not impact
waters of the U.S.
After
the new cables are installed and commissioned into service the seven existing
cables will be removed from the lake. This work will involve the removal of
rock riprap placed to protect the existing cables and excavation of trenches to
expose the cables. This work will extend a maximum of 250 feet beyond ordinary
high water. The excavated material will be sidecast onto the lake bottom, the
cables will be removed, and the lake bottom will be restored to
pre-construction contours with the excavated material. This work will
temporarily impact about 0.6 acre of lake bottom. Within deeper portions of the
lake the cables will be removed using a barge and hoisting system that will
lift the cables off the lake bottom and onto the barge deck for disposal.
The application for the federal permit was filed
with the Corps in compliance with Section 10 of the Rivers and Harbors Act,
which provides for federal regulation of any work in, or affecting navigable
waters of the U.S.; and Section 404 of the Clean Water Act, which regulates the
discharge or fill of material in U.S. waters, including wetlands.
The
public notice, with more detailed information, can be viewed on the Corps
website at www.nae.usace.army.mil/Missions/Regulatory/PublicNotices.aspx.
Public
comments on this work proposed by Vermont Transco, LLC and New York Power
Authority (File # NAE-2014-1674) should be forwarded no later than April 29,
2016 to the U.S. Army Corps of Engineers, New England District, Vermont Project
Office (ATTN: Michael Adams), 11 Lincoln Street, Room 210, Essex Junction,
Vermont 05452. Additional information is available from Permit Project Manager Michael
Adams at 802-872-2893 or by email to michael.s.adams@usace.army.mil.