Regulatory/Permitting Public Notices

Results:
Tag: Maine
Clear
  • NAE-2021-03258

    https://go.mil/5l9r6p9utiThe proposed project will result in the discharge of fill material into 16,363 square feet (0.376 acre) of waters of the U.S. (i.e., palustrine forested wetlands) to facilitate the construction of Phase 2 of the existing subdivision adjacent to Portland Road in Saco, Maine.
  • NAE-2024-00883

    Expiration date: 7/22/2026

    https://go.mil/y5w8xj2lr3The applicant is requesting a DA permit to discharge fill into 8,450 square feet (sq. ft.) of wetlands associated with Hobbs Brook in order to construct Phase II of the Brookside Subdivision. The subdivision will consist of nineteen single family house lots. Four of the five
  • NAE-2023-00524

    Expiration date: 7/8/2026

    The applicant is requesting a DA permit to discharge fill in 34,724 square feet of wetlands in order to construct a new substation, switchyard, access road, and transmission poles. Once the new substation is operational, the existing Bolt Hill and Eliot substations and their associated
  • NAE-2025-02574

    Expiration date: 6/25/2026

    The project/review area is located approximately 950 feet east of the I-95 corridor and 275 feet from the Exit 124 on/off ramp intersection with Trafton Road at Latitude 44.505480 and Longitude -69.697840; in Waterville, Kennebec County, Maine.https://go.mil/ir9hrqu9nlRead the public notice here.
  • PROPOSED ISSUANCE OF THE DEPARTMENT OF THE ARMY MAINE AQUACULTURE PROGRAMMATIC GENERAL PERMIT

    Expiration date: 4/21/2026

    PROPOSED ISSUANCE OF THE DEPARTMENT OF THE ARMY MAINE AQUACULTURE PROGRAMMATIC GENERAL PERMIThttps://go.mil/27cfqsgbtuRead the public notice here.  
  • NAE-2026-00243

    Expiration date: 4/22/2026

    TO WHOM IT MAY CONCERN: The New England District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344). The purpose of this public notice is to solicit comments from the public regarding the work described below:
  • NAE-2021-01340

    Expiration date: 4/12/2026

    TO WHOM IT MAY CONCERN: The New England District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344). The purpose of this public notice is to solicit comments from the public regarding the work described below:
  • NAE-2024-01866

    Expiration date: 3/28/2026

    TO WHOM IT MAY CONCERN: The New England District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344). The purpose of this public notice is to solicit comments from the public regarding the work described below:
  • NAE-2025-02520

    Expiration date: 4/12/2026

    TO WHOM IT MAY CONCERN: The New England District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344). The purpose of this public notice is to solicit comments from the public regarding the work described below:
  • NAE-2026-000009

    Expiration date: 3/31/2027

    The U.S. Army Corps of Engineers (Corps) New England District Regulatory Division issues the following Regional Conditions (RCs) to ensure that activities authorized by the 2026 Nationwide Permits (NWPs) in the New England states of Connecticut, Maine, Massachusetts, New Hampshire, Rhode Island, and Vermont will not cause more than minimal adverse environmental impacts, both individually and cumulatively. Before the New England District will verify an activity under one or more NWPs, the activity must be demonstrated to comply with the applicable NWP terms and all applicable NWP General Conditions (GCs) and RCs. Prior to commencement of a “non-notifying” activity (i.e., activities authorized by NWPs which do not require submission of a pre-construction notification [PCN]), the proponent (i.e., the person and/or the entity performing the work) is responsible for ensuring the activity meets all applicable: • Terms of the NWP • GCs • RCs • State Water Quality Certification, if applicable • State Coastal Zone Consistency, if applicable