Regulatory/Permitting Public Notices

  • NAE-2004-01359

    Expiration date: 9/12/2026

    The applicant proposes to remove the existing, deteriorated marina and travel liftstructures at 722 River Road and replace them with a new, expanded facility. Theproject includes the construction of a new floating dock system, a travel lift, associateddredging, and shoreline protection measures,
  • NAE-2026-00470

    Expiration date: 9/11/2026

    The proposed development would result in the discharge of fill material into 37,322 square feet (SF) (0.85 acre) of forested and scrub-shrub wetland to construct 14 single-family home lots and two multi-unit apartment buildings. 48 apartments are proposed. Proposed infrastructure would also include
  • NAE-2014-01550

    Expiration date: 9/2/2026

    The project proposes to complete maintenance dredging to support navigation of both private and commercial boats over a period of ten years at both Polpis Harbor and Hither Creek. The maintenance dredging proposes up to 15,800 cubic yards in Polpis Harbor measuring up to 74,500 square feet and up to
  • NAE-2009-01348

    Expiration date: 8/28/2026

    https://go.mil/vckc5t2275The proposed activity has the potential to generate stream and wetland mitigation credits within the ILF Program’s Upper Hudson Service Area (Figure 1). The 124.45-acre Batten Kill Mitigation Site would restore, enhance, and preserve freshwater wetlands and riparian buffer
  • NAE-2009-02001

    Expiration date: 8/28/2026

    The applicant proposes to complete annual maintenance dredging of the inlet throughthe barrier spit immediately south of an updrift jetty over a period of ten years. Themaintenance dredging will follow the previously established property line alignmentwithin the marsh to re-establish the direct
  • NAE-1997-01302

    Expiration date: 8/22/2026

    The applicant requests authorization to complete 342,017 square feet (37,299 cubic yards) of maintenance dredging within previously authorized areas of the West and North Bay Entrance Channel to a depth of - 11 ft MLLW (West Bay) and 8 ft MLLW (North Bay) with 1 foot of over dredge and 3H:1V side
  • NAE-2005-01142

    Expiration date: 8/22/2026

    The proposed activity has the potential to generate mitigation stream credits within the Salmon Falls – Piscataqua River ILF Program Service Area. The Gonic Dams Removal Project restored stream channel, aquatic organism passage, and riparian buffer along a segment the Cocheco River, near 73
  • NAE-2026-00931

    Expiration date: 8/23/2026

     The applicant is requesting a DA permit to discharge dredged or fill material in the North Branch of the Deerfield River to remove an existing dam, replace a culvert, and construct stormwater treatment facilities.  The permit can be seen here.https://go.mil/iu15m3ceoy
  • NAE-2005-00499

    Expiration date: 8/19/2026

    The applicant is requesting a DA permit to mechanically dredge approximately 28,000 square feet (11,000 cubic yards (cy)) of material to a depth of minus 5 feet mean lower low water (MLLW) plus one foot of allowable overdepth from shoaled areas totaling 1.8 acres of the marina’s property, located in
  • NAE-2021-03258

    https://go.mil/5l9r6p9utiThe proposed project will result in the discharge of fill material into 16,363 square feet (0.376 acre) of waters of the U.S. (i.e., palustrine forested wetlands) to facilitate the construction of Phase 2 of the existing subdivision adjacent to Portland Road in Saco, Maine.