Paddlers hit whitewater rapids during the 52nd Annual River Rat Race April 12 on the Athol-Orange section of the Millers River in Massachusetts. Water was released by the U.S. Army Corps of Engineers from both Birch Hill and Tully Lake dams in Royalston with flows of approximately 1,100 cubic feet per second (cfs) from Birch Hill Dam and 300 cfs from Tully Lake Dam for the event, according to Project Manager Jeffrey Mangum in Royalston.
The New England District and Tantara Associated Corporation installed fall protection barricade railings all over Fort Rodman, New Bedford, Massachusetts.

ArticleCS

Civil War fort now safer to visit

U.S. Army Corps of Engineers, New England District
Published Feb. 28, 2015
The New England District and Tantara Associated Corporation installed fall protection barricade railings all over Fort Rodman, New Bedford, Massachusetts.

The New England District and Tantara Associated Corporation installed fall protection barricade railings all over Fort Rodman, New Bedford, Massachusetts.

Visiting a piece of New Bedford, Massachusetts history just got a lot safer, due to efforts made by the New England District and its contractor.

The District and its contractor, Tantara Associates Corporation of Worcester, Massachusetts, completed the fabrication and installation of fall protection barricade railing at Fort Rodman in New Bedford. The barricade railing work falls under the Corps’ Defense Environmental Restoration Program for Formerly Used Defense Sites.

According to the Fort Taber/Fort Rodman Historical Association, Inc., Fort Rodman, formerly known as Fort Taber after the New Bedford mayor responsible for getting the structure built, was constructed during the Civil War to protect the port from enemy invasion. 

The granite walls at the fort were completed in 1863. In 1898, the fort and the surrounding military reservation was renamed after Lt. Col. William Logan Rodman of New Bedford who was killed during the Civil War. The last of six concrete batteries constructed, Battery Miliken, was completed in 1920. The fort was declared surplus in World War II but served as an Army Reserve Training area until the end of the Vietnam War.

Work consisted of fabricating and installing new steel barricade railing composed of galvanized solid steels posts, solid rails and solid balusters, with an overall height of approximately four feet. Additional work involved including minor grading and new ground cover material as well as clearing brush as needed to access the rail installation locations.

Tantara Associates Corporation, a woman-owned, small business contractor, also installed railing on the roof of the fort to create a panoramic viewing area of the park and Buzzard’s Bay. Challenges during the project included clearing heavy and thick vegetation at Battery Miliken and working with deteriorated concrete at the batteries that created unsafe conditions. In several instances some of the post locations for the barricade railing were designed to avoid unsound concrete and the project was successfully completed.

Work on the $524,732 project began in June 2014 and was completed the following December. After a final inspection conducted with New Bedford’s Park and Recreation and Planning Departments in January, the project was handed over to the city.

Dave Larsen was the Project Manager. Other team members involved in this project were: Susanne Grant, Project Engineer, Jim Morocco, Administrative Contracting Officer/Resident Engineer, Matt Tessier, Mark DeSouza, Jeff Gaeta, Kirk Bargerhuff and Marc Paiva of Engineering and Peg Lorenzo of Real Estate.

The Pawcatuck River Coastal Storm Risk Management Feasibility Study

   This proposed plan is presented  to facilitate public involvement in the review and commenting on the remedy selection process for the Nantucket Memorial Airport (NMA) Formerly Used Defense Site (FUDS.) 
    The Army Corps of Engineers is proposing a No Action under the Comprehensive Environmental Response, Compensation, and Liability Act for the Munitions Response Site-1, Project Number D01MA049901 at NMA located on Nantucket Island, MA.  The proposal was prepared using the Guide to Preparing Superfund Proposed Plans, Records of Decision, and Other Remedy Selection Decision Documents (USEPA, 1999).
    The final decision for NMA Site-1 site will be made after reviewing and considering all information submitted during the public comment period. The proposed decision may be modified based on new information or public comments. The public is encouraged to review and comment on the proposed plan.
    The FUDS program addresses the potential explosives safety, health, and environmental issues resulting from past munitions use at former defense sites under the Department of Defense (DoD) Military Munitions Response Program, established by the U.S. Congress under the Defense Environmental Restoration Program.  
    FUDS only applies to properties that transferred from DoD before October 17, 1986 and the first priority of USACE is the protection of human health, safety, and the environment. 
    The Army is the executive agent for the FUDS Program, and USACE is the lead agency for investigation/reporting and remedial decision-making at this munitions site with regulatory support provided by the Massachusetts Department of Environmental Protection (MassDEP).